12mentions
2010first mention
2020last mention
under constructionfinal signal

Summary

City of Oakland expected to begin construction imminently on long-awaited improvements to the Tunnel Road/SR13/Hiller Drive intersection, Tunnel Road, and Caldecott Lane. Project includes new sidewalks, shared-use ramps, upgraded traffic signals, micro-surfacing, and continuous bike lanes.

infrastructure-transitsupportedmediumunder-construction

Site group: Caldecott / Upper Broadway mitigation corridor

Various locations near Rockridge BART, Broadway, and Caldecott Tunnel area

Aliases

Broadway road diet and Caldecott intersection improvementsBroadway/Caldecott streetscape and bike-pedestrian improvementsCaldecott Fourth Bore Settlement projectsCaldecott Settlement Agreement streetscape projects (Broadway/Tunnel Road)Caldecott Settlement infrastructure projectsCaldecott Settlement mitigation projectsCollege Avenue / Broadway Caldecott Settlement streetscape improvementsTunnel Road/Caldecott Lane bike and pedestrian improvementsUpper Broadway Road Diet (Caldecott Settlement project)

Timeline

2010_10

Caldecott Settlement mitigation projects

The City of Oakland received an $8 million Caldecott Tunnel 4th Bore settlement from Caltrans. Proposed mitigation projects in Rockridge include improved pedestrian crossings at Broadway/Keith and Broadway/Lawton intersections, bike lanes, soundwall studies, and BART bicycle parking. Community meeting set for November 8.

supportedproposedmedium
2010_11

Caldecott Settlement mitigation projects

Public meeting held November 8 at Kaiser Elementary School where 33 draft mitigation projects were presented by planning consultant Victoria Eisen. Most public interest focused on Broadway/Lawton intersection improvements ($400,000+). Soundwalls along Highway 24 also of high interest. Public comment period extended through November 22.

supportedproposedmedium
2011_05

Caldecott Fourth Bore Settlement projects

$8 million settlement agreement with Caltrans over the Caldecott Tunnel Fourth Bore EIR. Final project list released March 23 includes soundwall studies along SR-24, intersection improvements at Broadway/Keith, Broadway/Lawton, College/Miles, Claremont/Hudson, bicycle and pedestrian facilities, and AC Transit Route 51 improvements. Projects numbered 1-21 funded.

supportedapprovedmedium
2013_10

Caldecott Settlement infrastructure projects

City of Oakland staff present updates on Caldecott Settlement Agreement project costs, which have grown significantly. The $8 million settlement with Caltrans will not go as far as originally projected; projects include intersection improvements, bike/pedestrian facilities, soundwall studies, and BART bicycle parking.

neutralin-reviewmedium
2013_11

Broadway road diet and Caldecott intersection improvements

Proposed designs for the Upper Broadway 'road diet' funded with Caldecott Settlement Agreement funds: reducing traffic lanes from 4 to 3, adding bike lanes, high-visibility crosswalks, and pedestrian improvements between Broadway Terrace and Keith Avenue. Community meeting scheduled November 18.

mixedproposedmedium
2013_12

Broadway road diet and Caldecott intersection improvements

City staff presented proposed designs for the Upper Broadway road diet at a public meeting in mid-November at College Preparatory School. Support was expressed for the improvements as well as concern that lane reconfiguration may increase congestion during commute periods. Construction expected in 2015.

mixedin-reviewlow
2014_01

Caldecott Settlement infrastructure projects

City staff have finished reviewing public comments on the Caldecott Settlement project list. Six more projects are expected to be funded than previously reported due to cost savings and a Safe Routes to Transit grant. Updated project costs and designs presented at January RCPC Town Hall.

supportedin-reviewlow
2015_07

Caldecott Settlement Agreement streetscape projects (Broadway/Tunnel Road)

Construction of the first projects funded through an $8 million Caltrans settlement over the Caldecott Tunnel Fourth Bore environmental documentation is starting this summer. Improvements include a cycle-track on Broadway, pedestrian crossing enhancements, upper Broadway bike lanes, pathway and sidewalk improvements, and a new HAWK pedestrian signal at Lawton. Future phases include bike lanes and sidewalks on Tunnel Road and safer access to the Rockridge BART station.

supportedunder-constructionmedium
2015_10

Broadway/Caldecott streetscape and bike-pedestrian improvements

Multiple Caldecott Settlement Agreement-funded construction projects are scheduled: Oakland's first cycle-track on Broadway beginning winter 2015; Safe Routes to Transit improvements beginning summer 2016; and pedestrian/bicycle lane improvements at Tunnel Road/Hiller Drive intersection in fall 2016.

supportedproposedlow
2016_04

Upper Broadway Road Diet (Caldecott Settlement project)

Caldecott Settlement Agreement-funded road diet project for Upper Broadway. Planned improvements include lane reduction from 4 to 3, bicycle lanes on both sides, pedestrian HAWK signal at Lawton Avenue, improved crosswalks, and bulb-outs. City held open house April 18 to present designs and take questions.

neutralapprovedlow
2018_05

College Avenue / Broadway Caldecott Settlement streetscape improvements

Multiple public streetscape and infrastructure improvements funded by Oakland's Caldecott Tunnel settlement with Caltrans were reported in progress or planned: Broadway lane diet (nearly complete), bike lanes on Broadway and College Avenue, pedestrian improvements and bulb-outs at various intersections, and widening of sidewalk along Market Hall on College Avenue. Costs were running over estimates on some projects, raising concern not all listed projects would be funded.

mixedunder-constructionmedium
2020_06

Tunnel Road/Caldecott Lane bike and pedestrian improvements

City of Oakland expected to begin construction imminently on long-awaited improvements to the Tunnel Road/SR13/Hiller Drive intersection, Tunnel Road, and Caldecott Lane. Project includes new sidewalks, shared-use ramps, upgraded traffic signals, micro-surfacing, and continuous bike lanes.

neutralunder-constructionlow

Quotes

The city of Oakland received an $8 million settlement when it negotiated with Caltrans on the construction of the tunnel's 4th bore. The projects serve to mitigate the impacts of the new bore and to enhance pedestrian and bicycle facilities in the area that includes the Rockridge and Temescal districts.2010_10 - Fourth Bore Mitigation Funding Meeting article, 2010_11
Engineering studies for possible soundwalls along parts of SR-24 in the Rockridge area have been included on the final list of the Caldecott Fourth Bore Settlement projects.2011_05 - Soundwalls series intro, p. 4
$8 million Settlement Agreement with Caltrans over Caldecott Tunnel Fourth Bore EIR2011_05 - Article headline, p. 5
Unfortunately, as the detailed design of construction plans has unfolded, corresponding cost estimates have grown from the initial costs used to develop the list, in some cases significantly.2013_10 - Caldecott Settlement Project Costs article, October 2013
Plans for the project area on Broadway between Broadway Terrace and Keith Avenue include: Resurfacing the roadway; Reducing the number of traffic lanes from four to three (one lane in each direction, with a two-way center turn lane); Adding bicycle lanes on both sides of the street; Adding high-visibility crosswalks; Keeping existing on-street parking2013_11 - Broadway Road Diet article, November 2013